Hamburg school to replace gymnasium floor

Two-phase project will not interfere with summer programs


Make text smaller Make text larger




Hamburg Borough School will begin replacing the gymnasium floor on Monday, a project that is expected to be completed by Oct. 1.

The first phase of the project — originally scheduled to bring during spring break — involves asbestos abatement. Core samples showed that the adhesive layer connecting the plywood layer to the concrete sub-floor contained asbestos. In order to ensure student safety the entire project was delayed until the summer to remove the floors and asbestos abatement.

The original floor was composed of rubber and plywood, which was glued to a concrete sub-floor.

According to the Chief School Administrator Roger Jinks, Jr.

“We’ve had to make individual repairs to tears in the seems and in certain areas the floor is beginning to buckle.” Jinks said. “The warranty on a rubber floor is only 8-10 years and the basketball lines need to be repainted every summer. With hardwood, the lines are under polyurethane and are basically permanent.”

Phase one is demolition the bleachers will be removed and stored on the stage. From there, the flooring will be removed and the asbestos abatement can begin. Upon completion of demolition, the second phase of the project, construction of the new floor will begin.

“Our contractor is using a full containment method where the air will be constantly monitored inside and outside of the gym, with full verification it is all contained in the gym.” Jinks said.

With full containment in the gym and constant air monitoring, student safety can be ensured and the project will not affect the summer pre-school and special education programs.

The project should take 2 1/2 months to complete and the goal is to have everything completed by Oct. 1, 2014. So as not to disrupt the school year, contingencies are in place to ensure that students will receive their physical education when they return in September, such as holding gym classes outdoors in appropriate weather. When completed the gym will have a wall-to-wall hardwood floor.

“The reality is hardwood will give us many more years of use,” Jinks said. “Rubber is not as effective, (hardwood) is better for student safety. We are looking forward to it.”


Make text smaller Make text larger

MUST READ NEWS

Image Ogdensburg to solicit bids for Heater's Pond Dam
OGDENSBURG — Mayor Steve Ciasullo reported on June 12 the public bid for Heater's Pond Dam rehabilitation is scheduled to advertise in July, awarding the construction...
Image Spend your summer with Pass it Along
— This summer, Pass It Along will be offering many different programs for teens to participate in leadership, service and...
Image Hardyston wins Academic Bowl
In what may be considered as the 32nd Annual Sussex County Middle School Academic Bowl, the two teams representing Hardyston...
Image EPA proposes constructing water supply for those affected by toxic Mansfield Trail Dump site
BY ERIKA NORTON
The U.S. Environmental Protection Agency proposed a new project as part of their cleanup of the Mansfield Trail Dump...

VIDEOS


Sign up to get our newsletter emailed to you every week!

  • Enter your email address in the box below.
  • Select the newsletters you would like to subscribe to.
  • Click the 'SUBSCRIBE' button.

Comments

Pool Rules



MOST COMMENTED



Click on the ad above to print your coupon!
Weather in Lafayette, NJ